Standard 7: Realistic and participatory detailed implementation planning for program impact.
Develop, jointly with partners, an evidence-based detailed implementation plan that includes programmatic, financial, procurement, logistics and donor engagement activities.
Key Action 1 | Validate key project design decisions based on an updated review of the project operating context (risks, issues, and opportunities). |
Who |
Project manager/chief of party if part of the design process, or other designated individual with a thorough understanding of the project design; members of the project design/proposal development team; all available CRS and partner members of the project start-up/implementation team; head of programming and head of operations, if not part of the proposal development team; country representative; security staff and technical advisors as needed. |
When |
|
Key Action 2 | Organize a start-up workshop to orient the project team, partner staff, and key stakeholders to the project design and compliance requirements. |
Who |
Project manager/chief of party; Head of programming; head of operations; senior operations staff; MEAL staff; regional or headquarters (HQ) staff who may play a specific role in the project (e.g., IDEA staff, or an HQ or regional program and/or operations advisor); CRS and partner project team members. |
When |
Per the timing in the early start-up plan and per any donor requirements. Generally:
|
Key Action 3 | Update/refine the proposal activities schedule to develop a comprehensive detailed implementation plan for the first year of the project. |
Who |
Project manager/chief of party; CRS and partner programming and operations staff; CRS and partner senior management, especially for large, complex, or otherwise strategic projects; technical advisors and deputy regional directors, as applicable. |
When |
Per the timeline developed in the early start-up plan and any donor requirements. Generally:
|
Key Action 4 | Develop the project MEAL system. |
Who |
MEAL coordinator and project manager or chief of party; CRS and partner project team members (including CRS and partner project MEAL staff); ICT4D and supply chain management staff as required; additional CRS MEAL staff from the country program, region, and HQ as needed. |
When |
|