Standard 6: Early transition and start-up planning (including pre-award).
Transition from the design/proposal team to the project start-up team and plan and conduct early start-up activities.
Set up an appropriate project governance structure.
-
Why
Project governance establishes a management framework for decision-making. It helps move the project forward when decisions are needed beyond the project manager's or chief of party's authority and it ensures that the right decisions are taken at the right time and with the right degree of stakeholder participation. As summarized in A Guide to the PMD Pro, a project governance structure clarifies:
- Authority: Who has the power to make decisions and within what tolerance Project tolerances set clear parameters within which a project manager/chief of party (PM/CoP) can act autonomously—and make it clear when the PM/CoP needs to seek approval. Project tolerances describe the approved ranges of variation that a PM/CoP is authorized to oversee without seeking the endorsement of members of the project governance structure. Tolerances may relate to such things as budget and project timeframe, project scope and quality. For example, a project tolerance might describe the percent by which a project, or line items in a project, can over- or under-spend without the approval of members of the project governance structure; or the acceptable number of days of delay in the implementation schedule before approval from the project governance structure is required. levels.
- Accountability: Who is accountable for the success of the project.
-
Who
- Primary responsible: Project manager/chief of party (PM/CoP)
- The PM/CoP, or acting PM/CoP, works with the SMT to establish the governance structure and shares information with the members of the governance structure for decision-making from start-up through close-out.
- Others involved: Country representative (CR); country program senior management team (SMT); partner senior leadership; other stakeholders as appropriate
- The CR and SMT support the PM/CoP to determine what type of governance structure is most appropriate for the project;
- The CR supports the PM/CoP as needed in outreach to partners or other stakeholders who may be part of the governance structure;
- CRS and partner senior leadership and other stakeholders who are members of the project governance structure contribute to the finalization of the governance structure.
Ensure staff with appropriate experience and seniority lead governance structure set-up: If the governance structure is set up before the PM/CoP is in place, country program senior managers should take responsibility for this key action if the individual designated as acting PM/CoP is not highly experienced.
-
When
Set up the governance structure so that it is operational within the first month after project approval.
- For externally funded projects, set up the structure no later than three weeks after learning of the donor’s intent to fund.
- For other projects, within three weeks of project start-up.
Defining governance structures during project design phase: For complex projects, donors may require a description of the project governance structure in the project proposal. Defining a preliminary governance structure during project design may also be useful for other projects (e.g., multi-country projects). In these cases, during start-up, the focus is on refining and launching the previously defined structure.
-
How
Follow these steps to set up the project governance structure, telescoping as needed depending on project complexity:
- The PM/CoP, acting PM/CoP, or country program SMT reviews the project proposal to confirm what information, if any, was included about the project governance structure.
- Building on information in the project proposal, the PM/CoP works with the country program SMT to decide on or confirm the most appropriate project governance structure, which will vary depending on project size, complexity and risk.
- For smaller projects with one, or only a few, partners, a small, flexible governance structure, comprised of CRS senior management and key leadership from partner organizations, may suffice. For projects of limited scope and complexity, the governance structure could even consist of only the PM/CoP plus a single individual named as “project sponsorThe project sponsor is the individual or group that provides support for the project, and is accountable for enabling success. ” (e.g., the head of programming or CR).
- For large, multi-partner, and/or multi-country projects, an appropriate governance structure may include a project board representing a variety of stakeholder perspectives (CRS senior management, partners’ senior leadership, community representatives, government, and possibly donors).
Multi-country projects and project governance structures: Multi-country projects often have many layered and/or parallel project organizational structures. Clarity on project governance and decision-making authority is especially important for such projects, whether they are supported through CRS discretionary resources or external donor funding. Identify appropriate governance structure roles for individual country program senior leadership, regional staff, and headquarters (HQ) staff as applicable. A project charterA project charter is a document that formalizes the project governance structure including the roles, responsibilities, and norms of the governance structure, and establishes project tolerances and decision-making authority. that documents agreed project governance roles, norms, and decision-making authority is an essential reference for these types of projects, especially during staff transition.
- For a small, flexible governance structure, membership will likely be clear. It is nonetheless good practice for the PM/CoP to convene a start-up meeting with members of the small governance structure (e.g., PM/CoP, CR, partner director(s)). Address the following points in the meeting:
- Identify and document tolerances Project tolerances set clear parameters within which a project manager/chief of party (PM/CoP) can act autonomously—and make it clear when the PM/CoP needs to seek approval. Project tolerances describe the approved ranges of variation that a PM/CoP is authorized to oversee without seeking the endorsement of members of the project governance structure. Tolerances may relate to such things as budget and project timeframe, project scope and quality. For example, a project tolerance might describe the percent by which a project, or line items in a project, can over- or under-spend without the approval of members of the project governance structure; or the acceptable number of days of delay in the implementation schedule before approval from the project governance structure is required.
and norms, including who can make which decisions and how decisions will be made:
- Which decisions is the PM/CoP is authorized to make directly?
- Which decisions must be brought to the other members of the governance structure?
- Will the senior CRS representative make the final decision after considering recommendations from any other members of the governance structure, or will decisions be made through another process?
- Establish a schedule for governance structure meetings to review project status, risks and issues.
- Use the Project Charter Template to develop a simple project charterA project charter is a document that formalizes the project governance structure including the roles, responsibilities, and norms of the governance structure, and establishes project tolerances and decision-making authority. .
TIP: Though it was designed with complex structures in mind, the Sample Agenda: Meeting to Establish a Project Governance Structure may provide useful ideas even for simpler governance structures.
- If a more complex project governance structure is required, the PM/CoP, or CR if needed, works with partner senior leadership to confirm appropriate partner representatives for the governance structure. Keep the following in mind:
- Be clear on the required profiles of governance structure members. Members must have the authority to make decisions on behalf of their respective organizations
- Carefully analyze the dynamics of the proposed governance structure and its members, keeping in mind that collaboration and decision-making is usually easier with smaller groups.
- Click here for Additional considerations about membership in project governance structures.
- It is often useful to include stakeholders with different perspectives, including:
- Executive perspective, to assess whether the project overall is providing value and is sufficiently resourced.
- Senior representatives of the participating community/project beneficiary group, to provide perspective on whether the project is meeting the needs of the people who will use the outputs (this perspective is sometimes referred to as “senior user perspective”).
- Partners, government or other strategic contributors to project outputs, to provide perspective on whether the project will be able to deliver quality outputs as planned (this perspective is sometimes referred to as “senior supplier perspective”).
- It is often useful to include stakeholders with different perspectives, including:
- For a more complex project governance structure, the PM/CoP convenes a formal kick-off meeting of the members of the governance structure to establish tolerances Project tolerances set clear parameters within which a project manager/chief of party (PM/CoP) can act autonomously—and make it clear when the PM/CoP needs to seek approval. Project tolerances describe the approved ranges of variation that a PM/CoP is authorized to oversee without seeking the endorsement of members of the project governance structure. Tolerances may relate to such things as budget and project timeframe, project scope and quality. For example, a project tolerance might describe the percent by which a project, or line items in a project, can over- or under-spend without the approval of members of the project governance structure; or the acceptable number of days of delay in the implementation schedule before approval from the project governance structure is required. and working norms.
- Use the Sample Agenda: Meeting to Establish a Project Governance Structure as a starting point.
- Work with members of the governance structure to formalize decision-making processes and the PM's or CoP's decision-making scope and authority.
- Good practice is to document governance structure norms and tolerances in a project charterA project charter is a document that formalizes the project governance structure including the roles, responsibilities, and norms of the governance structure, and establishes project tolerances and decision-making authority. – see the Project Charter Template.
TIP: Consider organizing the governance structure kick-off meeting or first regular meeting around the time of the project start-up workshop, to take advantage of stakeholders’ likely participation in that workshop.
- The PM/CoP convenes the first regular meeting of the governance structure (see Sample Project Governance Standing Meeting Agenda), per the schedule and norms agreed in the kick-off meeting and documented in the project charter. These meetings continue during the implementation phase, and through project close-out.
- Consider organizing regular governance structure meetings around quarterly and annual project review meetings.
- The PM/CoP ensures that he/she, or a designated note-taker, documents each meeting and key decisions made; shares the minutes per the agreed norms; and posts them to Gateway.
-
Partnership
- A project governance structure provides a clear way to include partners in project decision-making.
- When engaging with partners about the establishment of a project governance structure, communicate clearly and transparently about the purpose of the governance structure and the required criteria/profile for governance structure members.
- When possible (based on CRS’ knowledge of the partner organization), invite specific individuals to represent the partner in the governance structure. Partners are autonomous organizations, and CRS should be open to partner suggestions of alternate representatives, if the alternate meets the criteria for members of the governance structure. CRS should emphasize that it is essential for the effective functioning of the governance structure that the partner representative is someone who can make decisions on behalf of the organization.
When CRS is a sub-recipient- As a sub-recipient, CRS does not have control over the wider project governance structure. Seek clarity from the prime on the governance structure, including prime and sub roles and responsibilities within the governance structure.
- When CRS has a significant role as a sub-recipient, CRS should participate in the project governance structure. During the project design phase, and ideally as part of negotiating any (pre)teaming agreementA teaming agreement is an agreement between two or more entities intended to increase their competitiveness by pooling resources to obtain and perform an award. This term is used frequently in consortia-based proposal development. Organizations sign pre-teaming agreements to commit to work together to prepare for an anticipated funding opportunity, and to formalize the organizations’ intent to jointly pursue the opportunity when released. , advocate to the prime to consider a governance structure that includes sub-recipients.
- If CRS participates in the overall project governance structure, ensure CRS is represented by an appropriate senior staff with sufficiently detailed knowledge of the project, and the ability to make decisions for CRS on behalf of the project.
- Depending on the scope and complexity of CRS’ sub-award, CRS may choose to establish a project governance structure specific to its sub-award, particularly if CRS will be working through implementing partners.
Emergency projects- Project governance structures are often established for a wider emergency response rather than individual emergency projects, as the situation is fluid and often requires decision-making and resources beyond the scope or authority of a single PM/CoP. In such situations, a clear and effective governance structure is critical, as several projects will report into it.
- CRS directly implements some emergency projects. Even in these situations, a governance structure that engages CRS leadership and other stakeholders (e.g., government, beneficiary, and donor representatives) is a best practice to ensure sound project management.
Key resources
Tools and templates
Other resources
-
A Guide to the PMD Pro: 2.2.2, project set up, pages 39–41; page 42, Project Charters
-
Prince2 Wiki for more information on project tolerances and project management
- Primary responsible: Project manager/chief of party (PM/CoP)